WindoorERP Documentation 19.0

Run an installation project on site

4 min read Updated 2026-08-30 WindoorERP 19.0

What this does

An installation project is the site-side container for a confirmed order: work packages hold the openings, each opening carries the actions that must be ticked off, and the whole thing rolls up into progress you can show a customer.

Before you start

  • The project is created when the sales order is confirmed with Create Project ticked — see Create a quotation. You do not normally create one by hand.
  • Installation tracking is switched on per database in Settings; if the Installation app is missing entirely, that switch is off.

Steps

Installation projects on a kanban board, grouped by site execution stage with per-project progress

An installation project form showing its work packages, assigned people and the progress rolled up from the items beneath

  1. 01
    Open Installation › Projects and find the job.
  2. 02
    Open the project to see its work packages — the tasks that group the work, typically by floor, elevation or phase.
  3. 03
    Open a work package to see its installation items: one row per opening, each with its own item code.
  4. 04
    On an item, tick the installation actions as they are completed on site; the item's state and the project's progress follow from them.
  5. 05
    Raise a snag against any item that needs returning to, and close it when the fix is done.

The three levels

LevelWhat it is
ProjectThe job on site, created from the confirmed sales order. Everything below it rolls up here.
Work packageA task grouping a set of openings — a floor, an elevation, a phase. It is what a foreman is given.
Installation itemOne opening, with its own item code, linked back to the order line it came from. Items can be split when one order line covers several physical units.
ActionA step on an item — the configured stages your company installs by. Ticking actions is what moves progress.

Note

Items are generated from the order's lines when the project is created, taking their codes from the line. Hand-created items get a generated ITEM- code instead — a quick way to tell later which openings came from the order and which were added on site.

Who can do what

An Installation User — installer or coordinator — ticks actions, splits items and updates progress. An Installation Manager additionally configures the action stages and can re-open a completed action, which requires a logged reason. Neither role can delete items, by design: work that happened stays on the record.

Troubleshooting

SymptomCause and fix
No project appeared after confirming the orderCreate Project was unticked on the order before confirmation, or installation tracking is off for the database. The setting locks after confirmation.
A project has no itemsIts order lines produced none — check that the lines are the fabricated ones the site will install.
You cannot delete an item added by mistakeDeletion is deliberately not granted. Ask a manager, or park the item rather than removing the record.
Progress does not move although work is doneProgress comes from ticked actions, not from dates or intentions. Tick them on site, or ask the crew to.
You can see other companies' projectsBackend access is company-scoped, not per-user; "my work" filtering exists on the dashboard and the portal, not in the full list.

Common mistakes

  • Managing the site in a spreadsheet and ticking the actions in a batch afterwards — the progress everyone else reads is then always a day stale.
  • Splitting an item after the actions were ticked instead of before work starts.
  • Recording a snag in a chat message rather than against the item it belongs to.
  • Re-opening a completed action without a reason worth reading later.

Was this article helpful?

Running a window or door factory?

Ask for a demo